"Enable All job Activity" vs. "Enable Scheduler" (Read 578 times)
02. Nov 2012 at 19:06

svcghost   Offline
YaBB Newbies
Commvault Support

Posts: 5
*
 
Hey guys. When you right click the commcell server --> Properties --> Activity Control tab, I am a bit confused.

There is an option to uncheck the "Enable All Job Activity", but also an option to "Enable Scheduler". What is the difference between leaving this scheduler checked or unchecked.

Here is what I think, please tell me if I am correct. If you leave "Enable Scheduler" checked, then all scheduled jobs are postponed until the job activity control is enabled again. If you uncheck the "Enable Scheduler" box, then scheduled jobs, if they are scheduled to run during the time range that job activity control is disabled, they will not run at all?
 